Safe Work Method Statement: Bulk earthworks

Doc ID: TCE-SWMS-001 · Version 1.0 · Approved 20 Oct 2026

1. Activity

Bulk earthworks including site strip, cut and fill, compaction and building pads with mobile plant. All workers must review this statement at prestart before work begins.

2. Job steps and controls

Risk ratings are shown before controls are applied.

Job stepHazardRiskControlsResponsible
Site set upPublic access, servicesHighFence and sign site; locate and mark services; induct all workers.Supervisor
Plant operationPlant and people interactionHighExclusion zones, spotters, two way radios, reversing cameras.Operators
Cut and fillBatter collapseHighBatter to geotech design; no work under unsupported faces.Supervisor
HaulageVehicle collisionMediumDefined haul roads, speed limits, water cart for dust.Drivers
Compaction testingStruck by plantMediumTesters stand clear; plant stopped while testing.Lab technician

3. Stop work

Stop work if conditions change, including rain, unexpected services or ground movement. Review controls with the crew and record changes before work resumes.